Eric functions as a group personality for an public team. He needs to arrange twenty-two soaking machines. He knows for 1 soaking machine, a initial line takes twenty-six minutes, a second line takes 33 minutes, as well as a final line takes twenty-eight minutes.
If you like this blog please take a second and subscribe to Home Improvement rss feed
Topics: assembly team, team leader, washing machine, washing machines
Comments: One comment
All the Home Improvement fields that are marked with REQ must be filled when searched for
J C
March 10th, 2011 at 1:48 pm
assuming any soaking appurtenance contingency go by all 3 lines:
26 + 33 + twenty-eight = 87minutes
87 X twenty-two machines = 1,914 minutes
1,914 / 60 mins in an hour = 31.9 hours
rounded to a nearest hour = 32 hours